Archives July 2022

Pool Concrete

While the pool was usable and very delightful after the initial installation, it obviously needed a concrete deck poured. I brought in Concrete Keith for the job, who had worked with me on the three season room and deck project last summer. He got to work pouring concrete, and the results were incredible. The first step was to pour a small ring of concrete around the pool, before pouring the rest of the deck and the stairs.

After that was done, he and his team poured and stamped the rest of the deck, along with a sloped walkway leading up to the pool from the hot tub area.

Now that the concrete is done, I have to wait a couple of weeks for it to fully cure on the inside before installing the railing and the pool cover, but until then there’s plenty of time to spend enjoying the pool!

Pool Installation

Despite the pool excavation being a little more involved than anticipated, the project to install the pool managed to roll on mostly on schedule. The Patio Pleasures team arrived, and started installing the pool walls and setting up the pump, filter, and heater.

Next, the plumbing went in, along with the liner, and we could start filling the pool. For the initial filling, we used a vacuum system to keep the liner tight along the walls and floor before the weight of the water took over. The installers also had to wait to cut the liner for the stairs until enough water had filled at the bottom of the pool.

While the pool started to fill, the electricians got to work wiring the pump and heater, running circuits for the pool lighting, and installing a grounding ring around the pool that grounds all metal and prevents us from getting electrocuting, which is a good thing.

We still had to wait for the pool to fill with enough water before moving on to the next step. I installed a WiFi smart faucet that allowed me to control filling remotely, since the pool could only be filled during daylight (so the liner could properly stretch) and needed around five days to fully fill.

After the water levels got high enough, the installers came back to cut in the liner around the stairs:

With the stairs cut in, the pool could start filling again. While that happened, the gas installers from Consumers Coop came and ran LP lines from our primary propane tank to the pool’s heater.

As the pool finished filling, I took care of some ancillary tasks like installing outdoor security cameras from Arlo and buying furniture for the pool deck.

With the pool full, I added chemicals and for the first time, we were able to use the pool!

Pool Excavation

After the grading for the pool was done and the land was surveyed, the next step was for the excavators to actually dig the hole for the pool, which turned into a much larger challenge than expected, and also turned into a logistical mess since I was coordinating the various contractors from Vegas (in a pool at the Wynn, which was sort of ironic given that this project also involves a pool).

The excavators started digging, and quickly encountered a huge limestone shelf that their equipment was unable to break through.

They then brought in heavier artillery, which also broke on the limestone:

Ultimately, I had to call in the original excavator who had done the grading, since he had heavier equipment than the excavator the pool installers had hired.

He was able to break through, and then we could start the pool installation!